Construction - Week 1 Day 6 - March 19, 2011
The block crew decided to work on Saturday. Friday night, we decided that we wanted to change the location of the crawl space access to provide a taller entry into the crawlspace area with the highest headroom. So, Camden and I had to get up early and race to the lot before the block wall got laid. We caught them just in time and made the change. Now we just have to make sure that we work the door into the landscaping to make sure it doesn't look out of place. After Day 6, there appears to be one more day of block work remaining.